Continuum Data Center Maintenance Schedule
Continuum Data Center | Continuum Business Park | Price Road and Continuum Street | Chandler, AZ
The Continuum Data Center Maintenance Schedule will be published on this website.
Planned maintenance windows are required for regular maintenance of the technology infrastructure that supports data center clients. These maintenance windows are key to the data center providing consistent and predictable service and help avoid unplanned downtime. Examples of work to be performed include equipment hardware maintenance, repair and upgrades, cleaning and flushing of systems, software upgrades and patching, and changes to improve performance and manageability of systems. All maintenance and outages will be scheduled for minimal disruption to clients as well as the surrounding community, and this site will provide advance notice and updates going forward.
Peter Enyeart Joshua Hughes
Facility Manager – PHX-04 Facility Manager – PHX-06
For questions or issues, please contact us via 480-729-8548 or [email protected]
Data Center Planned Maintenance Windows
Continuum Data Center – PHX-04
2900 W Innovation Street, Chandler, AZ 85286
| Month | Day | Duration | Maintenance Type |
|---|---|---|---|
| January | Monday - Friday (New Year's Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| February | Monday - Friday (President's Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test N. Gens |
| March | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test S. Gens |
| April | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| May | Monday - Friday (Memorial Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Annual Load Bank N. Gens |
| June | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Annual Load Bank S. Gens |
| July | Monday - Friday (4th of July Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| August | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test N. Gens |
| September | Monday - Friday (Labor Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Annual Transformer Test |
| October | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| November | Monday - Friday (Thanksgiving Eve & Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test N. Gens |
| December | Monday - Friday (Christmas Eve & Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test S. Gens |
Continuum Data Center – PHX-06
2955 W Innovation Street, Chandler, AZ 85286
| Month | Day | Duration | Maintenance Type |
|---|---|---|---|
| January | Monday - Friday (New Year's Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| February | Monday - Friday (President's Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test N. Gens |
| March | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test S. Gens |
| April | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| May | Monday - Friday (Memorial Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Annual Load Bank N. Gens |
| June | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Annual Load Bank S. Gens |
| July | Monday - Friday (4th of July Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| August | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test N. Gens |
| September | Monday - Friday (Labor Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Annual Transformer Test |
| October | Monday - Friday | 9:00 AM - 5:00 PM | Generator Monthly Run Test |
| November | Monday - Friday (Thanksgiving Eve & Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test N. Gens |
| December | Monday - Friday (Christmas Eve & Day Excluded) | 9:00 AM - 5:00 PM | Generator Monthly Run Test & Quarterly Test S. Gens |